Building work
Building work
Work: Technical facilities
Part 1 Ventilation
Period: November 2008 to April. 2010
Part 2 Sanitation
Period: January 2009 to April 2010
Part 3 Sprinklers / special installations
Period: January 2009 to April 2010
Part 4 Piping / Heating / Cold-air supply
Cold-air supply
Heating
Period: January 2009 to April 2010
Part 5 Insulation / fire prevention
Period: February 2009 to April 2010
Period: November 2008 to April 2010
Not applicable
Performance bond amounting to 10% of the net contract sum
Defects liability bond amounting to 5% of the net final-invoice amount
Subject to Part B of the Building Contract Code ("VOB/B") (payment period for instalments 18 working days / final invoice 30 working days)
Not applicable
Headquarters as specified in Point 1
Period for performance of work: see Point 3(a)
permitted
The elements and the planned performance of any work
concerned by proposed variants must be described in the bid in a
comprehensive and verifiable manner. Variants and supplementary bids
may be submitted only with a main bid.
European Patent Office
Central Procurement (Dept. 4.4.4)
Tender No.: 1356
Erhardtstrasse 27
D-80469 Munich
Postal address: EPO, D-80298 Munich.
Fax: +49 (0)89 2399-4497
mntenderclarifications@epo.org
The Procurement Documents may be requested by letter, fax or e mail.
The EPO does not expect to send the Procurement Documents before early
June 2008 and would therefore ask bidders to refrain from requesting
clarification before then.
6 June 2008, 12.00 hrs (CET)
16 June 2008, 12.00 hrs (CET)
queries must be submitted by letter, fax or e mail.
27 June 2008, 12.00 hrs (CET)
Two copies, in addition to the original bid to be marked as such
The bid must be filed in writing by post or courier service; bids submitted by fax or e-mail will be eliminated.
As in Point 6(a), but please note the requirements in Point 6(d)
German
The Procurement Documents are available only in German.
If several bidders submit a joint bid, one must be designated as prime contractor responsible for performance of all obligations under the contract.
See Procurement Documents
Seven months as from final date for submitting bids as per point 6(d) above
Criteria group I: Economic efficiency (weighting 70%)
Criteria group II: Competence / capacity (weighting 30%)
The EPO reserves the right to invite bidders to a meeting to
clarify their bid. The costs incurred by bidders in attending such
meetings are not reimbursable.
It is planned to offer those bidding for the ventilation work (Part 1)
an opportunity to visit the object on 12/13 June 2008 on prior
arrangement of an appointment. Requests for an appointment must be sent
in writing by post, fax or e-mail to the address specified in Point
6(a) by 10 June 2008, 12:00 hrs. The request must quote the number of
this tender and the full name(s) of the person(s) who will be attending
on behalf of their firm. The EPO will inform bidders of the precise
time of the visit.
Contract award is expected to take place in the first week of November 2008.
NUTS Code: DE 212
CPV Codes: 29231230, 29715300, 45343230, 45343100